The US 550/I-25 project completion has been delayed until late December. The original completion date was scheduled for the first week of November. The contractor, FNF Construction, has cited numerous reasons for the delays, including utility conflicts and difficulties with … Continue reading

Posted in I-25/US 550 Interchange | Leave a comment

I-25/US 550 Interchange Reconstruction Has Begun

You may have noticed the “Road Work Ahead” signs that have been placed on I-25, US 550 and Highway 165. These are for the interchange reconstruction and the improvements to Highway 165 and US 550 between the interchange and NM … Continue reading

Posted in I-25/US 550 Interchange | Tagged , , , | 1 Comment

Finding of No Significant Impact issued for I-25/US 550 Interchange

A Finding of No Significant Impact (FONSI) has been issued by the Federal Highway Administration (FHWA) for the I-25/US 550 Interchange Reconstruction Project.  The Environmental Assessment and Input Synopsis ( a summary of the comments presented at the public hearing, … Continue reading

Posted in I-25/US 550 Interchange | Leave a comment

Placitas Letters of Map Revisions (LOMR’s)

Many of you have seen and wondered about  the legal notices in the Albuquerque Journal regarding changes to the Federal Emergency Management Agency’s (FEMA’s) floodplain mapping in certain Placitas areas.  While the use of taxpayer monies for flood control being … Continue reading

Posted in ESCAFCA - Flood Control Authority, Zoning and Land Use | Tagged , , | Leave a comment

I-25/US550 Interchange Update

Construction plans are currently being prepared for the 65% complete submittal.  These plans are due in mid-March.  ES-CA will request permission to leave a set of plans for public review at the Placitas library when they are complete.

Posted in I-25/US 550 Interchange | Tagged | Leave a comment

ESCAFCA and Your Property Taxes

I have been asked several times recently if property taxes will go down this year because Placitas and Algodones east of I-25 have been removed from the ESCAFCA boundaries. The short answer is NO, as part of the compromise bill … Continue reading

Posted in Property Taxes | Tagged , , , | Leave a comment

Update on the I-25/US 550 Interchange

As many of you have heard, the interchange at I-25 and US 550 is scheduled for reconstruction. The project is currently in the Environmental Assessment phase and numerous interchange configurations have been examined. The preferred alternative is a Single Point … Continue reading